swiftlet house

Introducing Our Milestone : Yan Nest Berhad’s First Swiftlet House

SSH 691

Completion date : 30 June 2025

SSH691 is the first dedicated swiftlet house we have successfully built. This marks our exciting entry into the sustainable production of premium, edible bird’s nests.

Strategically located and carefully designed to mimic the natural habitat preferred by swiftlets, this facility represents our commitment to quality, ethical practices, and innovation. It embodies our dedication to harnessing nature’s resources responsibly while meeting the demand for this exceptional natural product.

This inaugural swiftlet house is more than just a structure; it’s the foundation of our vision to become a trusted provider of high-grade edible bird’s nests, cultivated with care and respect for the environment.

Construction process date 23/5/2025

Construction process date 24/5/2025

Construction process date 26/5/2025

Construction process date 27/5/2025

Construction process date 29/5/2025

Construction process date 30/5/2025

Construction process date 31/5/2025

Construction process date 3/6/2025

Construction process date 5/6/2025

Construction process date 6/6/2025

Construction process date 10/6/2025

Construction process date 12/6/2025

Construction process date 13/6/2025

Construction process date 15/6/2025

Construction process date 16/6/2025

Construction process date 20/6/2025

Construction process date 21/6/2025

Construction process date 23/6/2025

Construction process date 26/6/2025

Construction process date 27/6/2025

Construction process date 14/7/2025

Construction process date 17/7/2025

Construction process date 19/7/2025

Construction process date 19/7/2025